Your construction schedule automatically adjusts for weekends and holidays!
* Delay your whole schedule with just 4 mouse clicks!

Construction Schedule - Your Building Project
Start
End
Task
Trade
Nov 3, 02 Nov 3, 02 Applications for utilities Supervisor
Nov 3, 02 Nov 3, 02 Clear lot Excavator
Nov 3, 02 Nov 3, 02 Establish lot boundaries Surveyor
Nov 3, 02 Nov 3, 02 Install culvert Supervisor
Nov 3, 02 Nov 3, 02 Material samples for environmental tester Supervisor
Nov 3, 02 Nov 3, 02 Set Benchmark Surveyor
Nov 3, 02 Nov 3, 02 Stake Lot Surveyor
Nov 3, 02 Nov 3, 02 Temporary power hookup Electrician
Nov 4, 02 Nov 5, 02 Excavate for services Excavator
Nov 4, 02 Nov 5, 02 Excavate for trench footings Excavator
Nov 4, 02 Nov 5, 02 Temporary driveway Supervisor
Nov 4, 02 Nov 7, 02 Excavate for basement Excavator
Nov 4, 02 Nov 8, 02 Remove excess fill Trucker
Nov 7, 02 Nov 8, 02 Conduit for electrical cable Electrician
Nov 7, 02 Nov 8, 02 Connect water well Plumber
Nov 7, 02 Nov 8, 02 Engineering report on soil stability Soils Engineer
Nov 7, 02 Nov 8, 02 Sewer connection Plumber
Nov 7, 02 Nov 8, 02 Storm sewer connection Plumber
Nov 7, 02 Nov 8, 02 Water connection Plumber
Nov 8, 02 Nov 8, 02 Deliver footing material Lumberyard
Nov 8, 02 Nov 14, 02 Form footings Foundation Contractor
Nov 13, 02 Nov 14, 02 Place reinforcing steel Reinforcing Steel Contractor
Nov 14, 02 Nov 14, 02 Call for footing inspection Supervisor
Nov 15, 02 Nov 15, 02 Footing inspection Foundation Contractor
Nov 15, 02 Nov 15, 02 Footing inspection Supervisor
Nov 18, 02 Nov 18, 02 Deliver concrete for footings Concrete Supplier
Nov 18, 02 Nov 18, 02 Pour footings Foundation Contractor
Nov 19, 02 Nov 19, 02 Deliver concrete forms Concrete Form Supplier
Nov 19, 02 Nov 19, 02 Deliver reinforcing steel Reinforcing Steel Supplier
Nov 19, 02 Nov 19, 02 Strip footings Foundation Contractor
Nov 19, 02 Nov 22, 02 Form walls Foundation Contractor
Nov 19, 02 Nov 25, 02 Place reinforcing steel Reinforcing Steel Contractor
Nov 22, 02 Nov 25, 02 Call for wall inspection Supervisor
Nov 22, 02 Nov 25, 02 Form for openings in wall Foundation Contractor
Nov 22, 02 Nov 25, 02 Prepare for imbedded anchors Foundation Contractor
Nov 25, 02 Nov 25, 02 Wall inspection Foundation Contractor
Nov 25, 02 Nov 25, 02 Wall inspection Supervisor
Nov 26, 02 Nov 26, 02 Deliver concrete for basement walls Concrete Supplier
Nov 26, 02 Nov 26, 02 Pour walls Foundation Contractor
Nov 27, 02 Nov 27, 02 Clear construction material Foundation Contractor
Nov 27, 02 Nov 27, 02 Deliver drainage pipes Lumberyard
Nov 27, 02 Nov 27, 02 Strip walls Foundation Contractor
Nov 27, 02 Nov 27, 02 Tar snap ties Foundation Contractor
Nov 28, 02 Nov 28, 02 Dampproof basement walls Dampproofer
Nov 28, 02 Nov 28, 02 Deliver granular Trucker
Nov 28, 02 Nov 28, 02 Place drainage pipes Drainage Contractor
Nov 28, 02 Nov 28, 02 Underslab electrical Electrician
Nov 28, 02 Nov 29, 02 Place granular Drainage Contractor
Nov 28, 02 Nov 29, 02 Underslab plumbing Plumber
Nov 29, 02 Nov 29, 02 Call for drainage inspection Supervisor
Dec 2, 02 Dec 2, 02 Drainage inspection Drainage Contractor
Dec 2, 02 Dec 2, 02 Drainage inspection Supervisor
Dec 2, 02 Dec 2, 02 Place window wells and drain pipes Supervisor
Dec 3, 02 Dec 3, 02 Backfill walls Excavator
Dec 3, 02 Dec 3, 02 Call for underslab inspection Supervisor
Dec 4, 02 Dec 4, 02 Underslab inspection Supervisor
Dec 4, 02 Dec 5, 02 Spread granular Laborer
Dec 5, 02 Dec 5, 02 Deliver concrete for basement slab Concrete Supplier
Dec 5, 02 Dec 5, 02 Place and finish concrete for basement slab Concrete Finisher
Dec 5, 02 Dec 5, 02 Prep for slab pour Concrete Finisher
Dec 5, 02 Dec 13, 02 Erect structural components Structural Erector
Dec 6, 02 Dec 6, 02 Deliver framing materials Lumberyard
Dec 6, 02 Dec 6, 02 Deliver structural components Structural Supplier
Dec 16, 02 Dec 16, 02 Deliver roof trusses Truss Supplier
Dec 17, 02 Dec 19, 02 Install truss systems Framer
Dec 20, 02 Dec 20, 02 Deliver exterior doors Window and Door Supplier
Dec 20, 02 Dec 20, 02 Deliver tubs and showers Plumbing Fixture Supplier
Dec 20, 02 Dec 20, 02 Deliver windows Window and Door Supplier
Dec 20, 02 Dec 20, 02 Store window screens Supervisor
Dec 23, 02 Dec 23, 02 Install roof vents Roofer
Dec 23, 02 Dec 24, 02 Install windows Framer
Dec 23, 02 Dec 25, 02 Install tubs and showers Plumber
Dec 23, 02 Dec 26, 02 Install vents through roof Plumber
Dec 23, 02 Dec 27, 02 Call for structural engineer's inspection Supervisor
Dec 25, 02 Dec 25, 02 Call for final structural inspection Supervisor
Dec 25, 02 Dec 25, 02 Call for fire inspection Supervisor
Dec 25, 02 Dec 25, 02 Structural engineer's inspection Supervisor
Dec 26, 02 Dec 26, 02 Deliver roofing materials Roofing Material Supplier
Dec 26, 02 Dec 26, 02 Final structural inspection Supervisor
Dec 26, 02 Dec 26, 02 Fire marshal inspection Supervisor
Dec 27, 02 Dec 27, 02 Waterproof building Roofer
Dec 30, 02 Jan 2, 03 Build deck Framer
Dec 30, 02 Jan 3, 03 Install roofing Roofer
Jan 2, 03 Jan 3, 03 Install roof flashing Roofer
Jan 3, 03 Jan 3, 03 Call for telephone prewire Supervisor
Jan 3, 03 Jan 3, 03 Confirm cabinet measure Supervisor
Jan 3, 03 Jan 3, 03 Install air barrier Supervisor
Jan 3, 03 Jan 7, 03 Install paper and stucco wire Stuccoer
Jan 3, 03 Jan 8, 03 Exterior prime painting Painter
Jan 6, 03 Jan 6, 03 Call for water heater inspection Supervisor
Jan 6, 03 Jan 6, 03 Install water heater Plumber
Jan 6, 03 Jan 6, 03 Rough-in cable Electrician
Jan 6, 03 Jan 6, 03 Rough-in security Electrician
Jan 6, 03 Jan 6, 03 Rough-in sound and communications Electrician
Jan 6, 03 Jan 6, 03 Rough-in vacuum Electrician
Jan 6, 03 Jan 7, 03 Specialty exteriors installation Supervisor
Jan 6, 03 Jan 10, 03 Rough-in plumbing Plumber
Jan 6, 03 Jan 15, 03 Rough-in electrical Electrician
Jan 6, 03 Jan 21, 03 Rough-in heating HVAC Contractor
Jan 6, 03 Feb 4, 03 Install brick veneer Bricklayer
Jan 9, 03 Jan 9, 03 Call for gas piping inspection Supervisor
Jan 9, 03 Jan 9, 03 Call for stucco wire inspection Supervisor
Jan 9, 03 Jan 9, 03 Install gas piping Plumber
Jan 9, 03 Jan 9, 03 Water heater inspection Supervisor
Jan 10, 03 Jan 10, 03 Call for plumbing inspection Supervisor
Jan 10, 03 Jan 10, 03 Clean plumbing debris Plumber
Jan 10, 03 Jan 10, 03 Gas piping inspection Supervisor
Jan 10, 03 Jan 10, 03 Procure chimneys Supervisor
Jan 10, 03 Jan 10, 03 Stucco wire inspection Supervisor
Jan 10, 03 Jan 15, 03 Install rough coat Stuccoer
Jan 14, 03 Jan 14, 03 Call for electrical inspection Electrician
Jan 14, 03 Jan 14, 03 Call for gas and other heating fuel service Supervisor
Jan 14, 03 Jan 14, 03 Clean electrical debris Electrician
Jan 14, 03 Jan 14, 03 Install chimneys Framer
Jan 14, 03 Jan 14, 03 Plumbing inspection Supervisor
Jan 15, 03 Jan 15, 03 Electrical inspection Electrician
Jan 16, 03 Jan 16, 03 Clean heating debris HVAC Contractor
Jan 16, 03 Jan 16, 03 Install overhead door(s) Overhead Door Installer
Jan 16, 03 Jan 21, 03 Install insulation and vapor barrier Insulator
Jan 21, 03 Jan 21, 03 Call for insulation inspection Supervisor
Jan 22, 03 Jan 22, 03 Insulation inspection Supervisor
Jan 22, 03 Jan 22, 03 Load drywall Drywaller
Jan 23, 03 Jan 29, 03 Board drywall Drywaller
Jan 27, 03 Feb 3, 03 Install stucco finish coat Stuccoer
Jan 30, 03 Jan 30, 03 Call for electrical hookup Supervisor
Jan 30, 03 Jan 30, 03 Ceiling insulation attic Insulator
Jan 30, 03 Feb 14, 03 Drywall tape, texture, sand and clean Drywaller
Feb 4, 03 Feb 5, 03 Install gutters and downspouts Gutter Contractor
Feb 4, 03 Feb 5, 03 Install soffits and shutters Sider
Feb 5, 03 Feb 5, 03 Caulking Calker
Feb 5, 03 Feb 5, 03 Install exterior conduit for lighting, cable TV Electrician
Feb 5, 03 Feb 10, 03 Final grade and forms for exterior slabs Concrete Finisher
Feb 5, 03 Feb 14, 03 Exterior painting Painter
Feb 7, 03 Feb 7, 03 Call for cable TV conduit wire Supervisor
Feb 10, 03 Feb 10, 03 Call for exterior slab inspection Supervisor
Feb 11, 03 Feb 11, 03 Exterior slab inspection Supervisor
Feb 12, 03 Feb 12, 03 Deliver concrete for exterior slab Concrete Supplier
Feb 12, 03 Feb 12, 03 Place and finish concrete for exterior slab Concrete Finisher
Feb 14, 03 Feb 14, 03 Deliver or truck topsoil Trucker
Feb 14, 03 Feb 21, 03 Landscaping Landscaper
Feb 17, 03 Feb 17, 03 Final grade Landscaper
Feb 17, 03 Feb 18, 03 Prime interior Painter
Feb 18, 03 Feb 18, 03 Cut and cap cleanouts Landscaper
Feb 18, 03 Feb 18, 03 Install shutoff access covers Landscaper
Feb 18, 03 Feb 19, 03 Sprinkler system Landscaper
Feb 19, 03 Feb 19, 03 Deliver cabinets Cabinet Supplier
Feb 19, 03 Feb 19, 03 Deliver millwork Millwork Supplier
Feb 19, 03 Feb 27, 03 Finish paint/stain Painter
Feb 20, 03 Feb 20, 03 Plants, trees, and shrubs Landscaper
Feb 20, 03 Feb 20, 03 Procure bathroom accessories Supervisor
Feb 20, 03 Feb 20, 03 Procure light fixtures Supervisor
Feb 20, 03 Feb 20, 03 Procure mirrors and medicine cabinets Supervisor
Feb 20, 03 Feb 20, 03 Procure tile Supervisor
Feb 20, 03 Feb 21, 03 Install cabinets Cabinet Installer
Feb 20, 03 Mar 7, 03 Finish carpentry Trim Carpenter
Feb 24, 03 Feb 24, 03 Install sod/turf Landscaper
Feb 24, 03 Feb 24, 03 Underlayment for flooring Trim Carpenter
Feb 25, 03 Feb 28, 03 Final electrical Electrician
Feb 25, 03 Mar 3, 03 Finish heating HVAC Contractor
Mar 3, 03 Mar 3, 03 Call for final electrical inspection Electrician
Mar 3, 03 Mar 4, 03 Final painting Painter
Mar 4, 03 Mar 4, 03 Final electrical inspection Supervisor
Mar 4, 03 Mar 5, 03 Ceramics Tile Setter
Mar 5, 03 Mar 6, 03 Install hardware Trim Carpenter
Mar 5, 03 Mar 6, 03 Install wallpaper Painter
Mar 6, 03 Mar 6, 03 Deliver appliances Appliance Supplier
Mar 6, 03 Mar 6, 03 Floor protection Laborer
Mar 6, 03 Mar 10, 03 Install Flooring Floor Installer
Mar 6, 03 Mar 10, 03 Mosaics and terrazzo Tile Setter
Mar 6, 03 Mar 11, 03 Closet shelving Trim Carpenter
Mar 10, 03 Mar 10, 03 Call for mechanical inspection Supervisor
Mar 10, 03 Mar 11, 03 Install bathroom accessories Trim Carpenter
Mar 10, 03 Mar 11, 03 Install mirrors and medicine cabinets Trim Carpenter
Mar 11, 03 Mar 11, 03 Call for occupancy inspection Supervisor
Mar 11, 03 Mar 11, 03 Call for plumbing inspection Supervisor
Mar 11, 03 Mar 11, 03 Deliver and install shower doors Shower Door Supplier
Mar 11, 03 Mar 11, 03 Final cleaning Laborer
Mar 11, 03 Mar 11, 03 Final painting checkout Painter
Mar 11, 03 Mar 11, 03 Install plumbing fixtures Plumber
Mar 11, 03 Mar 11, 03 Install window screens Laborer
Mar 11, 03 Mar 11, 03 Mechanical inspection Supervisor
Mar 12, 03 Mar 12, 03 Occupancy inspection Supervisor
Mar 12, 03 Mar 12, 03 Plumbing inspection Supervisor
Mar 12, 03 Mar 19, 03 Deficiencies Supervisor
Mar 20, 03 Mar 20, 03 Owners inspection Supervisor