|
|
Start
|
End
|
Task
|
Trade
|
|
Nov 3, 02 |
Nov 3, 02 |
Applications for utilities |
Supervisor |
|
Nov 3, 02 |
Nov 3, 02 |
Clear lot |
Excavator |
|
Nov 3, 02 |
Nov 3, 02 |
Establish lot boundaries |
Surveyor |
|
Nov 3, 02 |
Nov 3, 02 |
Install culvert |
Supervisor |
|
Nov 3, 02 |
Nov 3, 02 |
Material samples for environmental tester |
Supervisor |
|
Nov 3, 02 |
Nov 3, 02 |
Set Benchmark |
Surveyor |
|
Nov 3, 02 |
Nov 3, 02 |
Stake Lot |
Surveyor |
|
Nov 3, 02 |
Nov 3, 02 |
Temporary power hookup |
Electrician |
|
Nov 4, 02 |
Nov 5, 02 |
Excavate for services |
Excavator |
|
Nov 4, 02 |
Nov 5, 02 |
Excavate for trench footings |
Excavator |
|
Nov 4, 02 |
Nov 5, 02 |
Temporary driveway |
Supervisor |
|
Nov 4, 02 |
Nov 7, 02 |
Excavate for basement |
Excavator |
|
Nov 4, 02 |
Nov 8, 02 |
Remove excess fill |
Trucker |
|
Nov 7, 02 |
Nov 8, 02 |
Conduit for electrical cable |
Electrician |
|
Nov 7, 02 |
Nov 8, 02 |
Connect water well |
Plumber |
|
Nov 7, 02 |
Nov 8, 02 |
Engineering report on soil stability |
Soils Engineer |
|
Nov 7, 02 |
Nov 8, 02 |
Sewer connection |
Plumber |
|
Nov 7, 02 |
Nov 8, 02 |
Storm sewer connection |
Plumber |
|
Nov 7, 02 |
Nov 8, 02 |
Water connection |
Plumber |
|
Nov 8, 02 |
Nov 8, 02 |
Deliver footing material |
Lumberyard |
|
Nov 8, 02 |
Nov 14, 02 |
Form footings |
Foundation Contractor |
|
Nov 13, 02 |
Nov 14, 02 |
Place reinforcing steel |
Reinforcing Steel Contractor |
|
Nov 14, 02 |
Nov 14, 02 |
Call for footing inspection |
Supervisor |
|
Nov 15, 02 |
Nov 15, 02 |
Footing inspection |
Foundation Contractor |
|
Nov 15, 02 |
Nov 15, 02 |
Footing inspection |
Supervisor |
|
Nov 18, 02 |
Nov 18, 02 |
Deliver concrete for footings |
Concrete Supplier |
|
Nov 18, 02 |
Nov 18, 02 |
Pour footings |
Foundation Contractor |
|
Nov 19, 02 |
Nov 19, 02 |
Deliver concrete forms |
Concrete Form Supplier |
|
Nov 19, 02 |
Nov 19, 02 |
Deliver reinforcing steel |
Reinforcing Steel Supplier |
|
Nov 19, 02 |
Nov 19, 02 |
Strip footings |
Foundation Contractor |
|
Nov 19, 02 |
Nov 22, 02 |
Form walls |
Foundation Contractor |
|
Nov 19, 02 |
Nov 25, 02 |
Place reinforcing steel |
Reinforcing Steel Contractor |
|
Nov 22, 02 |
Nov 25, 02 |
Call for wall inspection |
Supervisor |
|
Nov 22, 02 |
Nov 25, 02 |
Form for openings in wall |
Foundation Contractor |
|
Nov 22, 02 |
Nov 25, 02 |
Prepare for imbedded anchors |
Foundation Contractor |
|
Nov 25, 02 |
Nov 25, 02 |
Wall inspection |
Foundation Contractor |
|
Nov 25, 02 |
Nov 25, 02 |
Wall inspection |
Supervisor |
|
Nov 26, 02 |
Nov 26, 02 |
Deliver concrete for basement walls |
Concrete Supplier |
|
Nov 26, 02 |
Nov 26, 02 |
Pour walls |
Foundation Contractor |
|
Nov 27, 02 |
Nov 27, 02 |
Clear construction material |
Foundation Contractor |
|
Nov 27, 02 |
Nov 27, 02 |
Deliver drainage pipes |
Lumberyard |
|
Nov 27, 02 |
Nov 27, 02 |
Strip walls |
Foundation Contractor |
|
Nov 27, 02 |
Nov 27, 02 |
Tar snap ties |
Foundation Contractor |
|
Nov 28, 02 |
Nov 28, 02 |
Dampproof basement walls |
Dampproofer |
|
Nov 28, 02 |
Nov 28, 02 |
Deliver granular |
Trucker |
|
Nov 28, 02 |
Nov 28, 02 |
Place drainage pipes |
Drainage Contractor |
|
Nov 28, 02 |
Nov 28, 02 |
Underslab electrical |
Electrician |
|
Nov 28, 02 |
Nov 29, 02 |
Place granular |
Drainage Contractor |
|
Nov 28, 02 |
Nov 29, 02 |
Underslab plumbing |
Plumber |
|
Nov 29, 02 |
Nov 29, 02 |
Call for drainage inspection |
Supervisor |
|
Dec 2, 02 |
Dec 2, 02 |
Drainage inspection |
Drainage Contractor |
|
Dec 2, 02 |
Dec 2, 02 |
Drainage inspection |
Supervisor |
|
Dec 2, 02 |
Dec 2, 02 |
Place window wells and drain pipes |
Supervisor |
|
Dec 3, 02 |
Dec 3, 02 |
Backfill walls |
Excavator |
|
Dec 3, 02 |
Dec 3, 02 |
Call for underslab inspection |
Supervisor |
|
Dec 4, 02 |
Dec 4, 02 |
Underslab inspection |
Supervisor |
|
Dec 4, 02 |
Dec 5, 02 |
Spread granular |
Laborer |
|
Dec 5, 02 |
Dec 5, 02 |
Deliver concrete for basement slab |
Concrete Supplier |
|
Dec 5, 02 |
Dec 5, 02 |
Place and finish concrete for basement slab |
Concrete Finisher |
|
Dec 5, 02 |
Dec 5, 02 |
Prep for slab pour |
Concrete Finisher |
|
Dec 5, 02 |
Dec 13, 02 |
Erect structural components |
Structural Erector |
|
Dec 6, 02 |
Dec 6, 02 |
Deliver framing materials |
Lumberyard |
|
Dec 6, 02 |
Dec 6, 02 |
Deliver structural components |
Structural Supplier |
|
Dec 16, 02 |
Dec 16, 02 |
Deliver roof trusses |
Truss Supplier |
|
Dec 17, 02 |
Dec 19, 02 |
Install truss systems |
Framer |
|
Dec 20, 02 |
Dec 20, 02 |
Deliver exterior doors |
Window and Door Supplier |
|
Dec 20, 02 |
Dec 20, 02 |
Deliver tubs and showers |
Plumbing Fixture Supplier |
|
Dec 20, 02 |
Dec 20, 02 |
Deliver windows |
Window and Door Supplier |
|
Dec 20, 02 |
Dec 20, 02 |
Store window screens |
Supervisor |
|
Dec 23, 02 |
Dec 23, 02 |
Install roof vents |
Roofer |
|
Dec 23, 02 |
Dec 24, 02 |
Install windows |
Framer |
|
Dec 23, 02 |
Dec 25, 02 |
Install tubs and showers |
Plumber |
|
Dec 23, 02 |
Dec 26, 02 |
Install vents through roof |
Plumber |
|
Dec 23, 02 |
Dec 27, 02 |
Call for structural engineer's inspection |
Supervisor |
|
Dec 25, 02 |
Dec 25, 02 |
Call for final structural inspection |
Supervisor |
|
Dec 25, 02 |
Dec 25, 02 |
Call for fire inspection |
Supervisor |
|
Dec 25, 02 |
Dec 25, 02 |
Structural engineer's inspection |
Supervisor |
|
Dec 26, 02 |
Dec 26, 02 |
Deliver roofing materials |
Roofing Material Supplier |
|
Dec 26, 02 |
Dec 26, 02 |
Final structural inspection |
Supervisor |
|
Dec 26, 02 |
Dec 26, 02 |
Fire marshal inspection |
Supervisor |
|
Dec 27, 02 |
Dec 27, 02 |
Waterproof building |
Roofer |
|
Dec 30, 02 |
Jan 2, 03 |
Build deck |
Framer |
|
Dec 30, 02 |
Jan 3, 03 |
Install roofing |
Roofer |
|
Jan 2, 03 |
Jan 3, 03 |
Install roof flashing |
Roofer |
|
Jan 3, 03 |
Jan 3, 03 |
Call for telephone prewire |
Supervisor |
|
Jan 3, 03 |
Jan 3, 03 |
Confirm cabinet measure |
Supervisor |
|
Jan 3, 03 |
Jan 3, 03 |
Install air barrier |
Supervisor |
|
Jan 3, 03 |
Jan 7, 03 |
Install paper and stucco wire |
Stuccoer |
|
Jan 3, 03 |
Jan 8, 03 |
Exterior prime painting |
Painter |
|
Jan 6, 03 |
Jan 6, 03 |
Call for water heater inspection |
Supervisor |
|
Jan 6, 03 |
Jan 6, 03 |
Install water heater |
Plumber |
|
Jan 6, 03 |
Jan 6, 03 |
Rough-in cable |
Electrician |
|
Jan 6, 03 |
Jan 6, 03 |
Rough-in security |
Electrician |
|
Jan 6, 03 |
Jan 6, 03 |
Rough-in sound and communications |
Electrician |
|
Jan 6, 03 |
Jan 6, 03 |
Rough-in vacuum |
Electrician |
|
Jan 6, 03 |
Jan 7, 03 |
Specialty exteriors installation |
Supervisor |
|
Jan 6, 03 |
Jan 10, 03 |
Rough-in plumbing |
Plumber |
|
Jan 6, 03 |
Jan 15, 03 |
Rough-in electrical |
Electrician |
|
Jan 6, 03 |
Jan 21, 03 |
Rough-in heating |
HVAC Contractor |
|
Jan 6, 03 |
Feb 4, 03 |
Install brick veneer |
Bricklayer |
|
Jan 9, 03 |
Jan 9, 03 |
Call for gas piping inspection |
Supervisor |
|
Jan 9, 03 |
Jan 9, 03 |
Call for stucco wire inspection |
Supervisor |
|
Jan 9, 03 |
Jan 9, 03 |
Install gas piping |
Plumber |
|
Jan 9, 03 |
Jan 9, 03 |
Water heater inspection |
Supervisor |
|
Jan 10, 03 |
Jan 10, 03 |
Call for plumbing inspection |
Supervisor |
|
Jan 10, 03 |
Jan 10, 03 |
Clean plumbing debris |
Plumber |
|
Jan 10, 03 |
Jan 10, 03 |
Gas piping inspection |
Supervisor |
|
Jan 10, 03 |
Jan 10, 03 |
Procure chimneys |
Supervisor |
|
Jan 10, 03 |
Jan 10, 03 |
Stucco wire inspection |
Supervisor |
|
Jan 10, 03 |
Jan 15, 03 |
Install rough coat |
Stuccoer |
|
Jan 14, 03 |
Jan 14, 03 |
Call for electrical inspection |
Electrician |
|
Jan 14, 03 |
Jan 14, 03 |
Call for gas and other heating fuel service |
Supervisor |
|
Jan 14, 03 |
Jan 14, 03 |
Clean electrical debris |
Electrician |
|
Jan 14, 03 |
Jan 14, 03 |
Install chimneys |
Framer |
|
Jan 14, 03 |
Jan 14, 03 |
Plumbing inspection |
Supervisor |
|
Jan 15, 03 |
Jan 15, 03 |
Electrical inspection |
Electrician |
|
Jan 16, 03 |
Jan 16, 03 |
Clean heating debris |
HVAC Contractor |
|
Jan 16, 03 |
Jan 16, 03 |
Install overhead door(s) |
Overhead Door Installer |
|
Jan 16, 03 |
Jan 21, 03 |
Install insulation and vapor barrier |
Insulator |
|
Jan 21, 03 |
Jan 21, 03 |
Call for insulation inspection |
Supervisor |
|
Jan 22, 03 |
Jan 22, 03 |
Insulation inspection |
Supervisor |
|
Jan 22, 03 |
Jan 22, 03 |
Load drywall |
Drywaller |
|
Jan 23, 03 |
Jan 29, 03 |
Board drywall |
Drywaller |
|
Jan 27, 03 |
Feb 3, 03 |
Install stucco finish coat |
Stuccoer |
|
Jan 30, 03 |
Jan 30, 03 |
Call for electrical hookup |
Supervisor |
|
Jan 30, 03 |
Jan 30, 03 |
Ceiling insulation attic |
Insulator |
|
Jan 30, 03 |
Feb 14, 03 |
Drywall tape, texture, sand and clean |
Drywaller |
|
Feb 4, 03 |
Feb 5, 03 |
Install gutters and downspouts |
Gutter Contractor |
|
Feb 4, 03 |
Feb 5, 03 |
Install soffits and shutters |
Sider |
|
Feb 5, 03 |
Feb 5, 03 |
Caulking |
Calker |
|
Feb 5, 03 |
Feb 5, 03 |
Install exterior conduit for lighting, cable TV |
Electrician |
|
Feb 5, 03 |
Feb 10, 03 |
Final grade and forms for exterior slabs |
Concrete Finisher |
|
Feb 5, 03 |
Feb 14, 03 |
Exterior painting |
Painter |
|
Feb 7, 03 |
Feb 7, 03 |
Call for cable TV conduit wire |
Supervisor |
|
Feb 10, 03 |
Feb 10, 03 |
Call for exterior slab inspection |
Supervisor |
|
Feb 11, 03 |
Feb 11, 03 |
Exterior slab inspection |
Supervisor |
|
Feb 12, 03 |
Feb 12, 03 |
Deliver concrete for exterior slab |
Concrete Supplier |
|
Feb 12, 03 |
Feb 12, 03 |
Place and finish concrete for exterior slab |
Concrete Finisher |
|
Feb 14, 03 |
Feb 14, 03 |
Deliver or truck topsoil |
Trucker |
|
Feb 14, 03 |
Feb 21, 03 |
Landscaping |
Landscaper |
|
Feb 17, 03 |
Feb 17, 03 |
Final grade |
Landscaper |
|
Feb 17, 03 |
Feb 18, 03 |
Prime interior |
Painter |
|
Feb 18, 03 |
Feb 18, 03 |
Cut and cap cleanouts |
Landscaper |
|
Feb 18, 03 |
Feb 18, 03 |
Install shutoff access covers |
Landscaper |
|
Feb 18, 03 |
Feb 19, 03 |
Sprinkler system |
Landscaper |
|
Feb 19, 03 |
Feb 19, 03 |
Deliver cabinets |
Cabinet Supplier |
|
Feb 19, 03 |
Feb 19, 03 |
Deliver millwork |
Millwork Supplier |
|
Feb 19, 03 |
Feb 27, 03 |
Finish paint/stain |
Painter |
|
Feb 20, 03 |
Feb 20, 03 |
Plants, trees, and shrubs |
Landscaper |
|
Feb 20, 03 |
Feb 20, 03 |
Procure bathroom accessories |
Supervisor |
|
Feb 20, 03 |
Feb 20, 03 |
Procure light fixtures |
Supervisor |
|
Feb 20, 03 |
Feb 20, 03 |
Procure mirrors and medicine cabinets |
Supervisor |
|
Feb 20, 03 |
Feb 20, 03 |
Procure tile |
Supervisor |
|
Feb 20, 03 |
Feb 21, 03 |
Install cabinets |
Cabinet Installer |
|
Feb 20, 03 |
Mar 7, 03 |
Finish carpentry |
Trim Carpenter |
|
Feb 24, 03 |
Feb 24, 03 |
Install sod/turf |
Landscaper |
|
Feb 24, 03 |
Feb 24, 03 |
Underlayment for flooring |
Trim Carpenter |
|
Feb 25, 03 |
Feb 28, 03 |
Final electrical |
Electrician |
|
Feb 25, 03 |
Mar 3, 03 |
Finish heating |
HVAC Contractor |
|
Mar 3, 03 |
Mar 3, 03 |
Call for final electrical inspection |
Electrician |
|
Mar 3, 03 |
Mar 4, 03 |
Final painting |
Painter |
|
Mar 4, 03 |
Mar 4, 03 |
Final electrical inspection |
Supervisor |
|
Mar 4, 03 |
Mar 5, 03 |
Ceramics |
Tile Setter |
|
Mar 5, 03 |
Mar 6, 03 |
Install hardware |
Trim Carpenter |
|
Mar 5, 03 |
Mar 6, 03 |
Install wallpaper |
Painter |
|
Mar 6, 03 |
Mar 6, 03 |
Deliver appliances |
Appliance Supplier |
|
Mar 6, 03 |
Mar 6, 03 |
Floor protection |
Laborer |
|
Mar 6, 03 |
Mar 10, 03 |
Install Flooring |
Floor Installer |
|
Mar 6, 03 |
Mar 10, 03 |
Mosaics and terrazzo |
Tile Setter |
|
Mar 6, 03 |
Mar 11, 03 |
Closet shelving |
Trim Carpenter |
|
Mar 10, 03 |
Mar 10, 03 |
Call for mechanical inspection |
Supervisor |
|
Mar 10, 03 |
Mar 11, 03 |
Install bathroom accessories |
Trim Carpenter |
|
Mar 10, 03 |
Mar 11, 03 |
Install mirrors and medicine cabinets |
Trim Carpenter |
|
Mar 11, 03 |
Mar 11, 03 |
Call for occupancy inspection |
Supervisor |
|
Mar 11, 03 |
Mar 11, 03 |
Call for plumbing inspection |
Supervisor |
|
Mar 11, 03 |
Mar 11, 03 |
Deliver and install shower doors |
Shower Door Supplier |
|
Mar 11, 03 |
Mar 11, 03 |
Final cleaning |
Laborer |
|
Mar 11, 03 |
Mar 11, 03 |
Final painting checkout |
Painter |
|
Mar 11, 03 |
Mar 11, 03 |
Install plumbing fixtures |
Plumber |
|
Mar 11, 03 |
Mar 11, 03 |
Install window screens |
Laborer |
|
Mar 11, 03 |
Mar 11, 03 |
Mechanical inspection |
Supervisor |
|
Mar 12, 03 |
Mar 12, 03 |
Occupancy inspection |
Supervisor |
|
Mar 12, 03 |
Mar 12, 03 |
Plumbing inspection |
Supervisor |
|
Mar 12, 03 |
Mar 19, 03 |
Deficiencies |
Supervisor |
|
Mar 20, 03 |
Mar 20, 03 |
Owners inspection |
Supervisor |
|